Photo a Day Challenge

GoDaddy’s New Call Center – May 22, 2014

GoDaddy  25
North West side of the building, the painting is coming along. Multiple coats of color should stand up to the sun for awhile.
GoDaddy  26
Lots of components for the air systems are stacked up on both floors. I’m sure changing the air filters will be a full time job.
GoDaddy  27
Insulation going into the exterior walls. Also insulation going into the interior walls for the restrooms/equipment rooms/ and offices.
GoDaddy  28
Some of the exterior walls are getting drywall. So much has changed in one week. The crews are taking a long weekend for Memorial Day, and then pushing towards the finish line. Carpet is scheduled for July 1st, and GoDaddy should take possession of the building in September.
GoDaddy  29
Windows are in on Phase I, the South East corner.
GoDaddy  30
This is the news everyone is waiting for…….. They have started hanging the basket cable trays. This will hold the hundreds of miles of cabling that will go into the call center. The open basket design helps keep the cables cool. All images taken with the Canon 5D Mark II, EF 24-105 F4 L lens, and most of the interior shots are lit with the Speedlight 580 EX II camera mounted. All of the images taken so far can be seen here.

Leave a Reply

Your email address will not be published.